Case Study

Building the Khulna 150MW Peaking Power Plant

Twenty-thousand cubic meters of cargo had to be delivered and installed in a crowded neighborhood of Goalpara, Khulna.

Khulna 150MW Power Plant

The project site was accessible only via a narrow one-way road, which was littered with buildings and shops, enmeshed with overhead wires and cables, and continually congested with trucks and lorries. All in all, building the Khulna 150MW Peaking Power Plant was no small feat, and yet, hardly an unfamiliar one for Conveyor Group.

View More

275MW Barapukuria Coal Fired Thermal Power Station

Conveyor Logistics Ltd. was employed to receive cargo at Ports of Entry (Mongla & Chittagong), inland transportation by road and river, and delivery at site.For Heavy-lift cargo,  especially Boiler Drum, weighing 199 Tons,

View More

Ashuganj 450MW Combined Cycle Power Plant (South), Ashuganj, Brahmanbaria, Bangladesh

Conveyor Logistics Limited (CLL) was employed to receive cargo at Ports of Entry (Mongla and Chittagong), inland transportation by road and river, and delivery at site. For some Heavy-lift cargo, especially the Gas Turbine (GT) weighing 306 Tons, Gas Turbine Generator (GTG) weighing 396 Tons,

View More

Siddhirganj 335MW Combined Cycle Power Plant

Conveyor Logistics Limited (CLL) was employed to receive cargo at Ports of Entry, inland transportation by road and river transport and delivery at site. For some Heavy-lift cargo, such as, the GE Gas Turbine (GT) weighing 280Ton, GE Gas Turbine Generator (GTG) weighing 222Ton.